Prime Realties

Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date75%3 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kanha HomesP52000017769Vadghar (Ct)2018Not reported28 Feb 2021—On date
Neera HomesP52000017922Vadghar (Ct)2018Not reported28 Feb 202128 Aug 2022+18 months
Prime CornerP52000017937Vadghar (Ct)2018Not reported28 Feb 2021—On date
Shree GaneshP52000018213Panvel2018Not reported30 Mar 2021—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kanha HomesOn date
  • Neera Homes+18 mo
  • Prime CornerOn date
  • Shree GaneshOn date

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Neera Homes (P52000017922).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology