Pride Purple Landmark Llp

Company or firm · 2 projects · 3 MahaRERA registrations

Projects23 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%3 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Park LandmarkP52100000809Pune (M Corp.)2017Not reported31 Oct 2018—On date
Park LandmarkP52100018741Pune (M Corp.)2018Not reported30 Dec 2022—On date
Park Landmark Phase IIIP52100047206Pune (M Corp.)2022Not reported31 Dec 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Park LandmarkOn date
  • Park LandmarkOn date
  • Park Landmark Phase IIIOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.