Pride Properties & Infrastructure
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 5 past their proposed date, not extended
+22 moMedian delayvs RERA proposed date · 5 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| SwargandhP52100009418 | Kothrud | 2017 | Certificate Signed | 5 Nov 2018 | 30 Oct 2020 | +23 months |
| Swami SamarthP52100015849 | Kothrud | 2018 | Certificate Signed | 1 Mar 2020 | 31 Dec 2024 | +57 months |
| ShreeP52100031012 | Kothrud | 2021 | Certificate Signed | 31 Dec 2024 | 31 Dec 2025 | +12 months |
| Vaibhavshree And Indira PriyadarshaniP52100032878 | Kothrud | 2022 | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 months |
| ShridharkrupaP52100033731 | Kothrud | 2022 | Certificate Signed | 31 Mar 2025 | 31 Jan 2027 | +22 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 57 months, for Swami Samarth (P52100015849).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology