Pride Builders Llp
Company or firm · 11 projects · 13 MahaRERA registrations
11Projects13 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date6 of 8 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 7 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| ManhattanP52100026529 | Charholi | 2020 | Certificate Signed | 1 Oct 2024 | 1 Oct 2024 | On date |
| AtlanticP52100031007 | Charholi | 2021 | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Wellington- A-BP52100031008 | Charholi | 2021 | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
| Wellington- N-OP52100032380 | Charholi | 2022 | Certificate Signed | 1 Sep 2025 | 1 Sep 2025 | On date |
| Manhattan-E BuildingP52100045218 | Charholi | 2022 | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
| Wellington-L-MP52100045786 | Charholi | 2022 | Certificate Signed | 1 Sep 2026 | 1 Jan 2027 | +4 months |
| SohoP52100046546 | Charholi | 2022 | Certificate Signed | 30 Apr 2026 | 30 Apr 2026 | On date |
| WellingtonP52100048477 | Charholi | 2023 | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 months |
| WellingtonP52100052379 | Charholi | 2023 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
| WellingtonP52100054534 | Charholi | 2024 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
| Miami A6-A7-B1P52100077670 | Charholi | 2024 | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 months |
| Miami A4-A5PR1260002502081 | Charoli | 2026 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
| Miami-A1-A2-A3-B2PR1260002600188 | Charoli | 2026 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
Show all 13 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 13 registrations
Track record notes
- 6 of 8 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Wellington-L-M (P52100045786).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology