Premnarayan Shukla
Individual promoter · 2 projects · 2 MahaRERA registrations
Also appears as PREMNARAYAN SHUKLA
2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Aditya VikasP51700016334 | Ambarnath(M Cl) | 2018 | Certificate Signed | 30 Sep 2018 | 30 Sep 2019 | +12 months |
| Aditya NishantP51700025307 | Ambarnath(M Cl) | 2020 | Certificate Signed | 29 Jan 2023 | 29 Jan 2023 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 12 months, for Aditya Vikas (P51700016334).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology