Prathmesh Developers
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Pooja Co-Op. Hsg. Soc. Ltd.P52100050283 | Pimpri Chinchawad (M Corp.) | 2023 | Certificate Signed | 31 Oct 2026 | 28 Feb 2027 | +4 months |
| Daffodil HomesP52100052560 | Pimpri Chinchawad (M Corp.) | 2023 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Samruddhi AshwamedhPR1260002500500 | Chinchwad | 2025 | Not reported | 30 Apr 2029 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- Longest extension on record: 4 months, for Pooja Co-Op. Hsg. Soc. Ltd. (P52100050283).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology