Prasad Estate

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai RadianceP52000006076Panvel2017Certificate Signed31 Oct 201831 Oct 2018On date
Sai PrasadP52000007874Panvel2017Certificate Signed30 Sep 201930 Mar 2022+30 months
Sai SafalyaP52000016178Panvel2018Certificate Signed30 Dec 202130 Dec 2021On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai RadianceOn date
  • Sai Prasad+30 mo
  • Sai SafalyaOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 30 months, for Sai Prasad (P52000007874).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology