Prarthana Enterprises

Company or firm · 1 project · 1 MahaRERA registration

1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+39 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai Shatabdi ResidencyP51700017821Manda2018Certificate Signed30 Dec 202031 Mar 2024+39 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai Shatabdi Residency+39 mo

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 39 months, for Sai Shatabdi Residency (P51700017821).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology