Prajapati Constructions Limited
Company or firm · 4 projects · 5 MahaRERA registrations
4Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
80%Kept RERA date4 of 5 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Prajapati ViharP52000002200 | Bokadvira | 2017 | Certificate Signed | 30 Jun 2018 | 30 Jun 2018 | On date |
| Prajapati OrnateP52000019057 | Panvel | 2018 | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Prajapati OpalP52000019078 | Panvel | 2018 | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Prajapati Opal Phase - IIP52000034824 | Panvel | 2022 | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
| Prajapati OrnateP52000035186 | Panvel | 2022 | Certificate Signed | 30 Jun 2026 | 30 Oct 2026 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Prajapati Ornate (P52000035186).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology