Pradnyaraj Properties

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Pradnyaraj LotusP52100007999Kharadi2017Not reported30 Dec 2021—On date
Pradnyaraj BudsP52100024131Vadgaonsheri2020Not reported30 Dec 202312 Aug 2024+8 months
Pradnyaraj ClassicP52100055311Wagholi2024Not reported30 Jul 202730 Jul 2027On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Pradnyaraj LotusOn date
  • Pradnyaraj Buds+8 mo
  • Pradnyaraj ClassicOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 8 months, for Pradnyaraj Buds (P52100024131).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology