Poonam Homemaker Llp

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+9 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Poonam Park View Phase IP99000002563Vasaivirar City (M Corp)2017Certificate Signed30 Jun 201930 Jun 2019On date
Poonam Park View Phase IIP99000016911Vasai2018Certificate Signed30 Jun 202130 Nov 2022+17 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Poonam Park View Phase IOn date
  • Poonam Park View Phase II+17 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 17 months, for Poonam Park View Phase II (P99000016911).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology