Polaris Developers

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Nexus GenesisPR1261012501959Kiwale2025Certificate Signed31 Dec 202930 Apr 2030+4 months
Nexus Genesis A and BPM1260002602314Kiwale2026Not reported30 Jun 2030—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Nexus Genesis+4 mo
  • Nexus Genesis A and BOn date

Track record notes

  • Longest extension on record: 4 months, for Nexus Genesis (PR1261012501959).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology