Platinum Lifespaces

Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%4 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Platinum CrescenzoP51700003954Navi Mumbai (M Corp.)2017Not reported30 Dec 2021—On date
One PlatinumP51700012154Navi Mumbai (M Corp.)2017Not reported29 Dec 202329 Dec 2023On date
Platinum EmporiusP52000015087Ulawe2018Not reported30 Dec 2022—On date
Platinum ExperioP52000022702Kalamboli2019Not reported30 Dec 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Platinum CrescenzoOn date
  • One PlatinumOn date
  • Platinum EmporiusOn date
  • Platinum ExperioOn date

Track record notes

  • 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology