Skip to content
Deedo home
Menu

Pioneer Developers

Company or firm · 2 projects · 2 MahaRERA registrations

Also appears as M/S PIONEER DEVELOPERS

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
GovindbaugP52100001469Pimpri Chinchawad (M Corp.)2017Certificate Signed31 May 202331 May 2023On date
Pioneer ResidencyP52100051111Pimpri Chinchawad (M Corp.)2023Not reported30 Jun 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • GovindbaugOn date
  • Pioneer ResidencyOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology