Pioneer Constructions
Company or firm · 5 projects · 6 MahaRERA registrations
Also appears as M/s Pioneer Constructions
5Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Golden BellsP52100003229 | Haveli | 2017 | Certificate Signed | 30 Dec 2018 | 30 Dec 2018 | On date |
| Golden BellsP52100004990 | Haveli | 2017 | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| VasantshreeP52100045708 | Dhankawadi | 2022 | Certificate Signed | 31 Dec 2024 | 30 Jun 2025 | +6 months |
| RevatiP52100053317 | Dhankawadi | 2023 | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
| Raj SalokhaPR1260002501219 | Kothrud | 2025 | Certificate Signed | 31 Aug 2028 | 31 Dec 2028 | +4 months |
| MarigoldPM1260002602260 | Dhankawadi | 2026 | Certificate Signed | 30 Jun 2030 | 30 Jun 2030 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 6 months, for Vasantshree (P52100045708).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology