Pinnacle Corporation

Company or firm · 3 projects · 4 MahaRERA registrations

3Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai TirthP51700020430Badlapur (M Cl)2019Certificate Signed30 Dec 202330 Dec 2023On date
Sai WorldP51700034155Badlapur (M Cl)2022Certificate Signed31 Mar 202631 Mar 2026On date
Sai TirthP51700034566Badlapur (M Cl)2022Certificate Signed31 Mar 202531 Mar 2025On date
Sai UniversePR1330002601334Badlapur2026Certificate Signed31 Dec 202930 Apr 2030+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai TirthOn date
  • Sai WorldOn date
  • Sai TirthOn date
  • Sai Universe+4 mo

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 4 months, for Sai Universe (PR1330002601334).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology