Pinnacle Corporation
Company or firm · 3 projects · 4 MahaRERA registrations
3Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date3 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sai TirthP51700020430 | Badlapur (M Cl) | 2019 | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Sai WorldP51700034155 | Badlapur (M Cl) | 2022 | Certificate Signed | 31 Mar 2026 | 31 Mar 2026 | On date |
| Sai TirthP51700034566 | Badlapur (M Cl) | 2022 | Certificate Signed | 31 Mar 2025 | 31 Mar 2025 | On date |
| Sai UniversePR1330002601334 | Badlapur | 2026 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Sai Universe (PR1330002601334).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology