Pimpri Chinchwad Municipal Corporation
Company or firm · 6 projects · 6 MahaRERA registrations
Projects66 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date60%3 of 5 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Pradhan Mantri Awas Yojana- CharholiP52100017367 | Charholi Kh | 2018 | Not reported | 30 Dec 2022 | 30 Dec 2023 | +12 months |
| Pradhan Mantri Awas Yojana-Pimpri R. No 77P52100020603 | Haveli | 2019 | Not reported | 21 Jun 2023 | 30 Nov 2023 | +5 months |
| Pradhan Mantri Awas Yojana- BorahdewadiP52100020929 | Haveli | 2019 | Not reported | 1 Aug 2023 | — | On date |
| EWS- AkurdiP52100026117 | Pimpri Chinchawad (M Corp.) | 2020 | Not reported | 30 Dec 2023 | — | On date |
| Pradhan Mantri Awas Yojana-DudulgaonP52100052195 | Dudulgaon | 2023 | Not reported | 30 Jun 2027 | — | On date |
| Pcmc Ews KiwalePR1260002600555 | Kiwale | 2026 | Not reported | 30 Jun 2026 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Pradhan Mantri Awas Yojana- Charholi (P52100017367).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology