Pegasus Properties Pvt. Ltd
Company or firm · 10 projects · 16 MahaRERA registrations
Also appears as Gera Projects Private Limited · Pegasus Properties Pvt. Ltd.
10Projects16 RERA registrations
0Completedas reported on MahaRERA project pages
85%Kept RERA date11 of 13 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Megapolis Symphony Phase IP52100000887 | Hinjavadi (Ct) | 2017 | Certificate Signed | 31 Jul 2022 | 31 Jul 2022 | On date |
| Megapolis MysticP52100001391 | Hinjavadi (Ct) | 2017 | Certificate Signed | 1 Mar 2020 | 1 Mar 2020 | On date |
| Megapolis SpringsP52100015188 | Hinjavadi (Ct) | 2018 | Certificate Signed | 27 Apr 2022 | 27 Apr 2022 | On date |
| Megapolis SpringsP52100016848 | Hinjavadi (Ct) | 2018 | Certificate Signed | 28 May 2022 | 28 May 2022 | On date |
| Megapolis SpringsP52100017386 | Hinjavadi (Ct) | 2018 | Certificate Signed | 30 Mar 2023 | 30 Mar 2023 | On date |
| Megapolis SpringsP52100018284 | Hinjavadi (Ct) | 2018 | Certificate Signed | 30 Mar 2023 | 29 Mar 2024 | +12 months |
| Megapolis Saffron - A3 to A9P52100018779 | Hinjavadi (Ct) | 2018 | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Megapolis MysticP52100019959 | Hinjavadi (Ct) | 2019 | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Megapolis Saffron - A10 to A14P52100021609 | Mulshi | 2019 | Certificate Signed | 30 Sep 2024 | 30 Sep 2024 | On date |
| Megapolis Serenity A8 to A12, B2 and Conv shop BP52100022957 | Mulshi | 2019 | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Megapolis Serenity A1 to A7, B1 and Conv shop AP52100023051 | Mulshi | 2019 | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Megapolis MysticP52100029121 | Hinjavadi (Ct) | 2021 | Certificate Signed | 27 Feb 2025 | 27 Feb 2025 | On date |
| Megapolis Saffron - ShopsP52100034988 | Hinjavadi (Ct) | 2022 | Certificate Signed | 31 Dec 2023 | 30 Dec 2024 | +12 months |
| Megapolis MysticP52100047674 | Hinjavadi (Ct) | 2022 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| Megapolis Shimmer - A1P52100052912 | Hinjavadi (Ct) | 2023 | Certificate Signed | 31 Mar 2029 | 31 Mar 2029 | On date |
| Joy on The Tree Tops Project AP52100077635 | Mulshi | 2024 | Certificate Signed | 3 Mar 2030 | 3 Jul 2030 | +4 months |
Show all 16 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 16 registrations
Track record notes
- 11 of 13 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Megapolis Springs (P52100018284).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 3 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology