Company or firm · 2 projects · 4 MahaRERA registrations

Projects24 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 4 past their proposed date, not extended
Median delay+9 movs RERA proposed date · 4 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Life Maxima Phase 1P52100002203Kirkatwadi2017Not reported31 Dec 202230 Jun 2023+6 months
Skyi Star CityP52100026727Kirkatwadi2020Not reported30 Mar 202429 Mar 2025+12 months
Skyi Star CityP52100029474Kirkatwadi2021Not reported31 Dec 202431 Dec 2025+12 months
Skyi Star CityP52100029481Kirkatwadi2021Not reported30 Sep 202431 Mar 2025+6 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Life Maxima Phase 1+6 mo
  • Skyi Star City+12 mo
  • Skyi Star City+12 mo
  • Skyi Star City+6 mo

Track record notes

  • 0 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Skyi Star City (P52100026727).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology