Pate Developers

Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 4 past their proposed date, not extended
Median delay+50 movs RERA proposed date · 4 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Countryside Phase 1P52100002809Sangarun2017Not reported31 Dec 201930 Mar 2024+51 months
Countryside Phase IIIP52100004089Sangarun2017Not reported31 Dec 201931 Dec 2024+60 months
Countryside Phase IIP52100005008Sangarun2017Not reported31 Dec 201930 Dec 2023+48 months
West Coast Park Phase IIP52100007669Shivne (Part)2017Not reported30 Jun 201915 Feb 2022+32 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Countryside Phase 1+51 mo
  • Countryside Phase III+60 mo
  • Countryside Phase II+48 mo
  • West Coast Park Phase II+32 mo

Track record notes

  • 0 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 60 months, for Countryside Phase III (P52100004089).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology