Pate Developers
Company or firm · 4 projects · 4 MahaRERA registrations
Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 4 past their proposed date, not extended
Median delay+50 movs RERA proposed date · 4 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Countryside Phase 1P52100002809 | Sangarun | 2017 | Not reported | 31 Dec 2019 | 30 Mar 2024 | +51 months |
| Countryside Phase IIIP52100004089 | Sangarun | 2017 | Not reported | 31 Dec 2019 | 31 Dec 2024 | +60 months |
| Countryside Phase IIP52100005008 | Sangarun | 2017 | Not reported | 31 Dec 2019 | 30 Dec 2023 | +48 months |
| West Coast Park Phase IIP52100007669 | Shivne (Part) | 2017 | Not reported | 30 Jun 2019 | 15 Feb 2022 | +32 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 60 months, for Countryside Phase III (P52100004089).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology