Parekh Infraprojects

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Deep AanganP51700001986Badlapur (M Cl)2017Not reported31 Dec 2019—On date
Deepali ResidencyP51700018470Badlapur (M Cl)2018Not reported30 Dec 2022—On date
Deep HomesP51700020366Badlapur (M Cl)2019Not reported30 Jun 202329 Jun 2024+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Deep AanganOn date
  • Deepali ResidencyOn date
  • Deep Homes+12 mo

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Deep Homes (P51700020366).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology