Param Builders And Developers

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Patels ResidencyP51700000865Ambarnath(M Cl)2017Certificate Signed31 Mar 201831 Mar 2019+12 months
Patels Residency - E WingP51700023093Ambarnath(M Cl)2019Not reported30 Dec 2023—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Patels Residency+12 mo
  • Patels Residency - E WingOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Patels Residency (P51700000865).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.