Paradigm Developers Private Limited
Company or firm · 3 projects · 3 MahaRERA registrations
3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Shree SnehP52100019371 | Haveli | 2019 | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| ManorP52100045930 | Baner | 2022 | Certificate Signed | 31 Dec 2024 | 31 Dec 2026 | +24 months |
| Paradigam VandanP52100079890 | Pimpri Chinchawad (M Corp.) | 2025 | Certificate Signed | 29 Feb 2028 | 29 Jun 2028 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 24 months, for Manor (P52100045930).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology