Pankaj Prakash Sawant

Individual promoter · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Suman ComplexP52000013923Karjat2017Not reported5 Oct 2023—On date
Pushkar ApartmentP52000024887Neral2020Not reported14 Feb 20231 Feb 2024+12 months
Prakash ComplexP52000055204Neral2024Not reported31 Mar 2029—On date
Vedant ComplexP52000080316Karjat2025Not reported31 Mar 2030—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Suman ComplexOn date
  • Pushkar Apartment+12 mo
  • Prakash ComplexOn date
  • Vedant ComplexOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Pushkar Apartment (P52000024887).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology