Pankaj Constructions

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
—Kept RERA dateno proposed date has passed yet
+4 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Gokul Greens Wing PearlP50500052734Nagpur (M Corp.)2023Certificate Signed31 Dec 202630 Apr 2027+4 months
Gokul Greens Wing CrystalP50500076920Nagpur (M Corp.)2024Certificate Signed31 Dec 202730 Apr 2028+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Gokul Greens Wing Pearl+4 mo
  • Gokul Greens Wing Crystal+4 mo

Track record notes

  • Longest extension on record: 4 months, for Gokul Greens Wing Pearl (P50500052734).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology