Pankaj Chandrakant Waghmare

Individual promoter · 5 projects · 6 MahaRERA registrations

Projects56 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
GladstoneP50500023032Gotal Panjari2019Not reported30 Dec 202130 Sep 2024+33 months
Unique Park - 5P50500046998Nagpur (Rural)2022Not reported31 Dec 2026—On date
Anandam Elite Phase - 4P50500053050Shankarpur2023Not reported31 Dec 2026—On date
Mauli TownP50500077758Nagpur (Rural)2024Not reported31 Dec 2027—On date
Mauli TownP50500077995Nagpur (Rural)2024Not reported31 Dec 2027—On date
Anandam Elite Phase VP50500080788Waroda2025Not reported31 Dec 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Gladstone+33 mo
  • Unique Park - 5On date
  • Anandam Elite Phase - 4On date
  • Mauli TownOn date
  • Mauli TownOn date
  • Anandam Elite Phase VOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 33 months, for Gladstone (P50500023032).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.