Pandit Nanabhau Molak

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sayali ComplexP52100008283Dehu2017Certificate Signed30 Sep 202030 Nov 2019On date
VighnahartaP52100080468Dehu2025Certificate Signed31 Mar 203031 Jul 2030+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sayali ComplexOn date
  • Vighnaharta+4 mo

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Vighnaharta (P52100080468).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology