Pancharatna Builcon Pvt. Ltd

Company or firm · 1 project · 4 MahaRERA registrations

1Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+20 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Nayantara PresidencyP51600000079Nashik (M Corp.)2017Certificate Signed30 Jun 202130 Mar 2025+45 months
Nayantara PresidencyP51600000098Nashik (M Corp.)2017Certificate Signed30 Mar 202830 Mar 2028On date
Nayantara PresidencyP51600000133Nashik (M Corp.)2017Certificate Signed30 Mar 202730 Jul 2027+4 months
Nayantara PresidencyP51600000245Nashik (M Corp.)2017Certificate Signed30 Jun 20219 May 2024+35 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Nayantara Presidency+45 mo
  • Nayantara PresidencyOn date
  • Nayantara Presidency+4 mo
  • Nayantara Presidency+35 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 45 months, for Nayantara Presidency (P51600000079).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology