Panch Tatva Realty
Company or firm · 1 project · 1 MahaRERA registration
1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+33 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Tridhaatu PrarambhP51800012185 | Kurla | 2017 | Certificate Signed | 30 Jun 2021 | 31 Mar 2024 | +33 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 33 months, for Tridhaatu Prarambh (P51800012185).
Regulatory cases across projects
- Regulatory orderRegulatory order: PROJECT NAME: TRIDHAATU PRARAMBH (REGULATORY CASE NO. 27 OF 2023) dated 13 July 2023. · Tridhaatu Prarambh · P51800012185 · 31 Jul 2023
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology