Padma Buildcon
Company or firm · 4 projects · 4 MahaRERA registrations · 2 reported completed
4Projects4 RERA registrations
2Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Padmaja ResidencyP51600013300 | Nashik (M Corp.) | 2017 | Completed | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| Padmaja AvenueP51600023198 | Nashik (M Corp.) | 2019 | Completed | 22 Oct 2023 | — | On date |
| Padmaja HeightsP51600030435 | Nashik (M Corp.) | 2021 | Certificate Signed | 20 Jul 2024 | 20 Jul 2024 | On date |
| PADMASHREE ApartmentP51600034162 | Nashik (M Corp.) | 2022 | Certificate Signed | 20 Dec 2024 | 20 Dec 2024 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Padmaja Residency (P51600013300).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology