Company or firm · 4 projects · 4 MahaRERA registrations · 2 reported completed

4Projects4 RERA registrations
2Completedas reported on MahaRERA project pages
75%Kept RERA date3 of 4 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Padmaja ResidencyP51600013300Nashik (M Corp.)2017Completed31 Dec 201831 Dec 2019+12 months
Padmaja AvenueP51600023198Nashik (M Corp.)2019Completed22 Oct 2023—On date
Padmaja HeightsP51600030435Nashik (M Corp.)2021Certificate Signed20 Jul 202420 Jul 2024On date
PADMASHREE ApartmentP51600034162Nashik (M Corp.)2022Certificate Signed20 Dec 202420 Dec 2024On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Padmaja Residency+12 mo
  • Padmaja AvenueOn date
  • Padmaja HeightsOn date
  • PADMASHREE ApartmentOn date

Track record notes

  • 3 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Padmaja Residency (P51600013300).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology