Oxy Flora Phase 2
Company or firm · 1 project · 1 MahaRERA registration
1Projects1 RERA registration
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 1 extended
1Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Oxy Flora Phase 2P52100015940 | Loni Kand | 2018 | Certificate Signed | 30 Dec 2021 | 31 Dec 2022 | +12 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Oxy Flora Phase 2 (P52100015940).
Regulatory cases across projects
- DeregisteredDeregistered: OXY FLORA PHASE 2 · Oxy Flora Phase 2 · P52100015940
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology