Company or firm · 3 projects · 3 MahaRERA registrations
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%2 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Redevelopment Of Loita Kunj Chs LtdP51800009064 | Mumbai | 2017 | Not reported | 30 Dec 2024 | 31 Dec 2025 | +12 months |
| Redevelopment Of The State Bank Of India Siddheshwar Co Op Housing Soc LtdP51800010846 | Kurla | 2017 | Not reported | 31 Dec 2017 | — | On date |
| Redevelopment Of State Bank Of India Employees Shree Co-Op Housing Soc LtdP51800010979 | Andheri | 2017 | Not reported | 30 Dec 2021 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Redevelopment Of Loita Kunj Chs Ltd (P51800009064).
Regulatory cases across projects
- Suo motu orderSuo motu order: Secretary, MahaRERA Versus M/s Orra Realtors Private Limited (Suo Motu Case No. 24 of 2019) dated 17th December 2019 · Redevelopment Of The State Bank Of India Siddheshwar Co Op Housing Soc Ltd · P51800010846 · 17 Dec 2019
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology