One Properties

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%1 of 2 past their proposed date, not extended
Median delay+6 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
One CornerP53000004976Kolhapur (M Corp.)2017Not reported31 Dec 201731 Dec 2018+12 months
White BoxP53000006511Kolhapur (M Corp.)2017Not reported31 Dec 2018—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • One Corner+12 mo
  • White BoxOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for One Corner (P53000004976).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology