Omkar Developers
Company or firm · 5 projects · 5 MahaRERA registrations
Also appears as M/S. OMKAR DEVELOPERS
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Mihir HeightsP52700006590 | Songirwadi (Rural) (Ct) | 2017 | Not reported | 31 Jan 2018 | 13 Jun 2024 | +77 months |
| omkar garden phase IIIP52700008193 | Sidhanathwadi (Rural) | 2017 | Not reported | 30 Sep 2020 | — | On date |
| Heera PalaceP52700023041 | Sidhanathwadi (Rural) | 2019 | Not reported | 31 Jul 2023 | — | On date |
| Omkars TaranganP52700029677 | Sidhanathwadi (Rural) | 2021 | Not reported | 31 Mar 2027 | — | On date |
| Swarngiri HeightsPM1300002601423 | Wai (M Cl) | 2026 | Not reported | 1 Mar 2031 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 77 months, for Mihir Heights (P52700006590).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology