Omega Premises Pvt Ltd
Company or firm · 6 projects · 6 MahaRERA registrations
6Projects6 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date3 of 6 past their proposed date, not extended
+5 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Mantri Mystica A PartP52100005136 | Pimpri Chinchawad (M Corp.) | 2017 | Certificate Signed | 31 Dec 2017 | 30 Sep 2019 | +21 months |
| Mantri Eternity PlusP52100007791 | Bhosari | 2017 | Certificate Signed | 25 Feb 2019 | 24 Feb 2020 | +12 months |
| Mantri Alpine C PartP52100011683 | Bavadhan Bk | 2017 | Certificate Signed | 31 Mar 2019 | 31 Mar 2019 | On date |
| Mantri Eternity BP52100011690 | Bhosari | 2017 | Certificate Signed | 31 Dec 2017 | 30 Sep 2018 | +9 months |
| Mantri Alpine C Phase IIIP52100022217 | Bavadhan Bk | 2019 | Certificate Signed | 31 Jul 2023 | 31 Jul 2023 | On date |
| Commerce CentreP52100023204 | Haveli | 2019 | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 21 months, for Mantri Mystica A Part (P52100005136).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology