Skip to content

Om Sai Ram Infra

Company or firm · 2 projects · 2 MahaRERA registrations

Also appears as M/S. Om Sai Ram Infra

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date1 of 1 past their proposed date, not extended
+2 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sitaram HeightsP99000027796Vada (Ct)2021Certificate Signed30 Jun 202530 Jun 2025On date
Swami EnclavePM1240002501138Vada (Ct)2025Certificate Signed31 Oct 202828 Feb 2029+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sitaram HeightsOn date
  • Swami Enclave+4 mo

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 4 months, for Swami Enclave (PM1240002501138).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology