Om Developers

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+6 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Om Yashlaxmi ApartmentP51700000576Kalyan2017Certificate Signed31 Dec 201931 Dec 2019On date
Navare PlazaP51700020680Dombivli2019Certificate Signed28 Aug 202228 Aug 2023+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Om Yashlaxmi ApartmentOn date
  • Navare Plaza+12 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Navare Plaza (P51700020680).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology