Om Chidanand Developers

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Audumbar A1 A2P52100028767Shivne (Part)2021Not reported1 Jun 202331 May 2024+11 months
Audumbar NestP52100079793Shivane (Uttamnagr)2025Not reported30 Dec 2026—On date
Audumbar Nest A1 A2 and B BuildingPR1260002500847Shivane (Uttamnagr)2025Not reported30 Dec 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Audumbar A1 A2+11 mo
  • Audumbar NestOn date
  • Audumbar Nest A1 A2 and B BuildingOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 11 months, for Audumbar A1 A2 (P52100028767).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology