Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 1 past their proposed date, not extended
+18 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ashoka HeightsP51800003394Kurla2017Certificate Signed30 Dec 202229 Dec 2025+36 months
Nahur Gaonthan Shiv Shakti Chs LtdP51800031723Kurla2021Not reported31 Mar 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ashoka Heights+36 mo
  • Nahur Gaonthan Shiv Shakti Chs LtdOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 36 months, for Ashoka Heights (P51800003394).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology