Nitin Vishnu Barve

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+9 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Janaki Niwas Phase IP52800017322Jalgaon2018Certificate Signed30 Nov 202030 Apr 2022+17 months
Janaki Niwas Phase IIP52800045611Jalgaon2022Certificate Signed31 May 202531 May 2025On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Janaki Niwas Phase I+17 mo
  • Janaki Niwas Phase IIOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 17 months, for Janaki Niwas Phase I (P52800017322).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology