Nitin Purushottam Badiyani

Individual promoter · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date2 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 0 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Yashodhan Phase 1 Building BP52700028070Karad2021Certificate Signed30 Dec 202230 Dec 2022On date
Yashodhan Phase 2 Building AP52700033624Karad2022Not reported31 Dec 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Yashodhan Phase 1 Building BOn date
  • Yashodhan Phase 2 Building AOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology