Individual promoter · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%2 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Aarya ResidencyP52600020040Solapur (M Corp.)2019Not reported30 Dec 2022—On date
Akshay LabhP52600024626Solapur (M Corp.)2020Not reported30 Dec 2022—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Aarya ResidencyOn date
  • Akshay LabhOn date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology