Nitin Dayalal Kothari

Individual promoter · 2 projects · 2 MahaRERA registrations · 2 reported completed

2Projects2 RERA registrations
2Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+29 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Kothari ChambersP51600006974Nashik2017Completed31 Dec 2018—On date
Monsoon MistP51600019135Pardevi2019Completed31 Mar 202031 Dec 2024+57 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Kothari ChambersOn date
  • Monsoon Mist+57 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 57 months, for Monsoon Mist (P51600019135).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology