Nirvana Leisure Realty

Company or firm · 2 projects · 4 MahaRERA registrations

Projects24 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 1 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
City Of Music Phase IP52000008728Bhilpada (Khuravale)2017Not reported30 Jun 2027—On date
City Of MusicP52000016821Bhilpada (Khuravale)2018Not reported30 Mar 202330 Jun 2026+39 months
City Of MusicP52000027911Bhilpada (Khuravale)2021Not reported31 Dec 2026—On date
City Of MusicP52000050052Bhilpada (Khuravale)2023Not reported31 Dec 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • City Of Music Phase IOn date
  • City Of Music+39 mo
  • City Of MusicOn date
  • City Of MusicOn date

Track record notes

  • 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 39 months, for City Of Music (P52000016821).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology