Nirmiti Vastu Creation Llp

Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 2 past their proposed date, not extended
Median delay+18 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Nirmiti 25 EastP52100002410Kharadi2017Not reported30 Mar 202428 Mar 2026+24 months
Nirmiti EliteP52100004507Pune (M Corp.)2017Not reported31 Jul 202230 Jul 2023+12 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Nirmiti 25 East+24 mo
  • Nirmiti Elite+12 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for Nirmiti 25 East (P52100002410).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology