Nirman Realtors And Developers Ltd
Company or firm · 5 projects · 8 MahaRERA registrations
5Projects8 RERA registrations
0Completedas reported on MahaRERA project pages
100%Kept RERA date5 of 5 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| VivianaP52000006083 | Dhamote | 2017 | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Nano CityP52000006161 | Bopele | 2017 | Certificate Signed | 31 Dec 2029 | 31 Dec 2029 | On date |
| VivianaP52000006209 | Dhamote | 2017 | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Sanskruti Building No 2 C WingP51800007436 | Andheri | 2017 | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 months |
| VivianaP52000007121 | Dhamote | 2017 | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Viviana - Block3P52000007537 | Dhamote | 2017 | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
| Green AcresP51800010794 | Borivali | 2017 | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| VivianaP52000012071 | Dhamote | 2017 | Certificate Signed | 30 Dec 2025 | 30 Dec 2025 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 5 of 5 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 4 months, for Sanskruti Building No 2 C Wing (P51800007436).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology