Nirman Estate Developers Pvt Ltd

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Nirman DwarkapuramP51600001184Nashik2017Certificate Signed30 Jun 202030 Jun 2020On date
Nirman Vrindavan Gardens Phase 3P51600014656Nashik2017Certificate Signed28 Feb 202131 Dec 2025+58 months
Nirmans MangalumP51600018587Aanandwali2018Certificate Signed8 Dec 20228 Dec 2022On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Nirman DwarkapuramOn date
  • Nirman Vrindavan Gardens Phase 3+58 mo
  • Nirmans MangalumOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 58 months, for Nirman Vrindavan Gardens Phase 3 (P51600014656).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology