Nirmal Lifestyle Ltd
Company or firm · 5 projects · 5 MahaRERA registrations
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
20%Kept RERA date1 of 5 past their proposed date, not extended
+60 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Nirmal Lifestyle-ZirconP51800004719 | Kurla | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| Nirmal Lifestyle-Blu Diamond-One EditionP51800006693 | Kurla | 2017 | Certificate Signed | 31 Aug 2019 | 31 Dec 2024 | +64 months |
| Nirmal Lifestyle-DiscoveryP51800006781 | Kurla | 2017 | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Nirmal Lifestyle-AmethystP51800010841 | Kurla | 2017 | Certificate Signed | 31 Mar 2019 | 30 Jun 2026 | +87 months |
| Nirmal Lifestyle, Triumph And ThrillP51800012493 | Kurla | 2017 | Certificate Signed | 31 Dec 2020 | 31 Dec 2025 | +60 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 5 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 87 months, for Nirmal Lifestyle-Amethyst (P51800010841).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology