Nirmal Lifestyle Ltd

Company or firm · 5 projects · 5 MahaRERA registrations

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
20%Kept RERA date1 of 5 past their proposed date, not extended
+60 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Nirmal Lifestyle-ZirconP51800004719Kurla2017Certificate Signed31 Dec 201831 Dec 2019+12 months
Nirmal Lifestyle-Blu Diamond-One EditionP51800006693Kurla2017Certificate Signed31 Aug 201931 Dec 2024+64 months
Nirmal Lifestyle-DiscoveryP51800006781Kurla2017Certificate Signed30 Dec 202330 Dec 2023On date
Nirmal Lifestyle-AmethystP51800010841Kurla2017Certificate Signed31 Mar 201930 Jun 2026+87 months
Nirmal Lifestyle, Triumph And ThrillP51800012493Kurla2017Certificate Signed31 Dec 202031 Dec 2025+60 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Nirmal Lifestyle-Zircon+12 mo
  • Nirmal Lifestyle-Blu Diamond-One Edition+64 mo
  • Nirmal Lifestyle-DiscoveryOn date
  • Nirmal Lifestyle-Amethyst+87 mo
  • Nirmal Lifestyle, Triumph And Thrill+60 mo

Track record notes

  • 1 of 5 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 87 months, for Nirmal Lifestyle-Amethyst (P51800010841).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology