Nirban Infrastructure Pvt Ltd
Company or firm · 5 projects · 5 MahaRERA registrations
Also appears as NIRBAN INFRASTRUCTURE PRIVATE LIMITED
5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Bismillah ResidencyP51900008056 | Ward E | 2017 | Certificate Signed | 31 Jul 2018 | 31 Jul 2019 | +12 months |
| Bismillah Residency Phase IIP51900020441 | Ward E | 2019 | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Bismillah EliteP51900031646 | Mumbai City | 2021 | Certificate Signed | 31 Mar 2027 | 31 Mar 2027 | On date |
| Bismillah Space ResidencyP51900054797 | Ward E | 2024 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
| Nirban NestlingsPM1170002501575 | Mumbai City | 2025 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 12 months, for Bismillah Residency (P51900008056).
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology