Nirban Infrastructure Pvt Ltd

Company or firm · 5 projects · 5 MahaRERA registrations

Also appears as NIRBAN INFRASTRUCTURE PRIVATE LIMITED

5Projects5 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+4 moMedian delayvs RERA proposed date · 3 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Bismillah ResidencyP51900008056Ward E2017Certificate Signed31 Jul 201831 Jul 2019+12 months
Bismillah Residency Phase IIP51900020441Ward E2019Certificate Signed30 Dec 202130 Dec 2021On date
Bismillah EliteP51900031646Mumbai City2021Certificate Signed31 Mar 202731 Mar 2027On date
Bismillah Space ResidencyP51900054797Ward E2024Certificate Signed31 Dec 202730 Apr 2028+4 months
Nirban NestlingsPM1170002501575Mumbai City2025Certificate Signed31 Dec 202930 Apr 2030+4 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Bismillah Residency+12 mo
  • Bismillah Residency Phase IIOn date
  • Bismillah EliteOn date
  • Bismillah Space Residency+4 mo
  • Nirban Nestlings+4 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 12 months, for Bismillah Residency (P51900008056).
  • No MahaRERA regulatory order or list names these registrations.
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology