Nilesh Shivjee Singh

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+60 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Tara CityP52100009317Lonikalbhor2017Certificate Signed31 Dec 201831 Dec 2018On date
Tara MondesireP52100011353Uruli Kanchan2017Certificate Signed31 Dec 201831 Oct 2025+82 months
Tara AthenaP52100012400Kesnand2017Certificate Signed31 Dec 201815 Dec 2023+60 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Tara CityOn date
  • Tara Mondesire+82 mo
  • Tara Athena+60 mo

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 82 months, for Tara Mondesire (P52100011353).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology